Fig. 01 / Project 06 of 06 / Partial scan
Local grid / 1 : 400
Vantaa Station RoofHelsinki, 2026
- Area
- 12 000 m²
- Year
- 2026
- Structure
- Timber
- Status
- In progress
Fig. 02 / Drawing set / Plan, section, elevation, axonometric
Fine lines drawn from the model / point cloud on the last tab
Drawn fromthe same model.
Every drawing below comes from the model the building was built and scanned against, with its grid, levels and the dimensions the site team worked to.
Fig. 03 / Scan vs design / As built against as drawn
Grey under 3 mm / blue over 8 mm
The building,against its drawing.
Drag the handle to compare the design with the latest scan. Each point is coloured by how far the built surface sits from the drawn one.
6 mm / Gridshell node on grid line 14
Fig. 04 / Construction / Survey to handover
Later milestones are upcoming
Construction timeline
- Survey / Done
- Foundations / Done
- Structure / In progress
- Envelope / Upcoming
- Handover / Upcoming
- Survey
- Foundations
- Structure / In progress
- Envelope / Upcoming
- Handover / Upcoming
Feb 2024 to Apr 2027 / 38 months
Fig. 05 / Credits / Team
Everyone who built it
Credits
- Client
- Vantaa Rail Partnership
- Structure
- Kehä Timber Engineering
- Services
- Raide Systems
- Contractor
- Pohjola Rakennus
- Scan imagery
- Norrvik
Fig. 06 / Narrative / What the model found
About 200 words
About the project
- Client
- Vantaa Rail Partnership
- Location
- Helsinki / Finland
- Sensors
- 248
The Vantaa Station Roof is a 12 000 m² timber gridshell over four platforms of a commuter station north of Helsinki, spanning the tracks without a single column on the platforms. Its 1 860 nodes join two families of curved timber lamellas into a shell that rises from the platform edges to almost eight metres above the rails.
The roof is still under construction, so what you see here is a partial scan: the built half captured weekly by drone and total station, the rest drawn as the design model. Each node is scanned as it is placed and compared with the fabrication model before the next row of lamellas goes up, and any deviation above six millimetres reaches the site team within the hour. Construction is at 58 percent. The 248 sensors installed during the build will stay for the life of the roof, and monitored energy data begins at handover.
Fig. 07 / Energy / 24 months monitored
kWh per m² per month / dashed line is the target
Energy use,month by month.
- Last 12 months
- 55 kWh/m² design
- Monthly target
- 4.6 kWh/m²
- Months at or under target
- From handover
- Embodied carbon
- 196 kgCO2e/m²
Monitoring begins at handover. The dashed blue line is the design target.
| Period | Measured |
|---|---|
| Oct 24 | No data |
| Nov 24 | No data |
| Dec 24 | No data |
| Jan 25 | No data |
| Feb 25 | No data |
| Mar 25 | No data |
| Apr 25 | No data |
| May 25 | No data |
| Jun 25 | No data |
| Jul 25 | No data |
| Aug 25 | No data |
| Sep 25 | No data |
| Oct 25 | No data |
| Nov 25 | No data |
| Dec 25 | No data |
| Jan 26 | No data |
| Feb 26 | No data |
| Mar 26 | No data |
| Apr 26 | No data |
| May 26 | No data |
| Jun 26 | No data |
| Jul 26 | No data |
| Aug 26 | No data |
| Sep 26 | No data |
Fig. 08 / Materials / Structural mass
Share by weight, as built
| Material | Share |
|---|---|
| Timber | 64% |
| Steel | 16% |
| Concrete | 12% |
| Glass | 6% |
| Other | 2% |
Fig. 09 / Lessons learned / Carried into the next model
03 entries
- L01Lesson learnedCompare every node before the next row goes up. Errors compound along a lamella.
- L02Lesson learnedWeekly drone capture kept the site model within one day of the real build.
- L03Lesson learnedDesign the monitoring network with the structure, not after handover.