Skip to content

Fig. 01 / Project 05 of 06 / Point cloud

Local grid / 1 : 400

All projects

Ribeira Bridge PavilionPorto, 2021

Area
640 m²
Year
2021
Structure
Steel
Status
Complete

Fig. 02 / Drawing set / Plan, section, elevation, axonometric

Fine lines drawn from the model / point cloud on the last tab

Drawn fromthe same model.

Every drawing below comes from the model the building was built and scanned against, with its grid, levels and the dimensions the site team worked to.

123AB24 0009 00010 000Waiting roomBridge deckRiverN05 mSCALE 1:200

Fig. 03 / Scan vs design / As built against as drawn

Grey under 3 mm / blue over 8 mm

The building,against its drawing.

Drag the handle to compare the design with the latest scan. Each point is coloured by how far the built surface sits from the drawn one.

9 0004 200+0.00+1.50+4.20Waiting roomBridge deckRoof plate tip05 mSCALE 1:150DESIGNAS BUILT

18 mm / Roof plate tip on the bridge side

Fig. 04 / Construction / Survey to handover

All milestones complete

Construction timeline

  1. Survey / Done
  2. Foundations / Done
  3. Structure / Done
  4. Envelope / Done
  5. Handover / Done

Nov 2019 to May 2021 / 18 months

Fig. 05 / Credits / Team

Everyone who built it

Credits

Client
Douro River Transit
Structure
Ponte Engenharia de Estruturas
Services
Douro Sistemas
Contractor
Metalúrgica do Freixo
Scan imagery
Norrvik

Fig. 06 / Narrative / What the model found

About 200 words

About the project

Client
Douro River Transit
Location
Porto / Portugal
Sensors
34

The Ribeira Bridge Pavilion is a 640 m² steel pavilion for river transport tickets and shelter at the foot of the Ribeira bridges in Porto. A single folded steel roof, 42 metres long, rests on eleven slender columns set back from the quay, so the view along the Douro stays open beneath it and the old riverfront keeps its line.

Steel this thin on a windy river edge needed proof as well as calculation. Strain gauges and accelerometers were fixed to the roof before it was lifted into place, which made it the first project we monitored from the first day of construction. The highest gust recorded so far reached 31 metres per second, and the roof deflected 18 millimetres at its free edge, within two millimetres of the prediction. Three years of matching data let the client extend the structural inspection interval from six months to a year, and the same gauges now count fatigue cycles at every connection.

Fig. 07 / Energy / 24 months monitored

kWh per m² per month / dashed line is the target

Energy use,month by month.

Last 12 months
41 kWh/m²
Monthly target
3.6 kWh/m²
Months at or under target
14 / 24
Embodied carbon
188 kgCO2e/m²
Monitored energy use for Ribeira Bridge Pavilion, kWh per square metre per month
PeriodMeasured
Oct 243 kWh/m²
Nov 243.4 kWh/m²
Dec 244.2 kWh/m²
Jan 254.3 kWh/m²
Feb 254 kWh/m²
Mar 253.4 kWh/m²
Apr 253 kWh/m²
May 252.9 kWh/m²
Jun 253.3 kWh/m²
Jul 253.9 kWh/m²
Aug 253.9 kWh/m²
Sep 253.2 kWh/m²
Oct 252.9 kWh/m²
Nov 253.3 kWh/m²
Dec 254 kWh/m²
Jan 264.2 kWh/m²
Feb 263.9 kWh/m²
Mar 263.3 kWh/m²
Apr 263 kWh/m²
May 262.9 kWh/m²
Jun 263.2 kWh/m²
Jul 263.7 kWh/m²
Aug 263.7 kWh/m²
Sep 262.9 kWh/m²
Monthly energy use per square metre of floor area, Oct 24 to Sep 26. The dashed blue line is the design target.

Fig. 08 / Materials / Structural mass

Share by weight, as built

Share of structural mass by material, Ribeira Bridge Pavilion
MaterialShare
Steel58%
Concrete22%
Glass14%
Timber3%
Other3%

Fig. 09 / Lessons learned / Carried into the next model

03 entries

  1. L01Lesson learnedFix the gauges before the lift. The first day of load is the one you cannot recreate.
  2. L02Lesson learnedMeasured deflection within 2 mm of prediction bought a longer inspection interval.
  3. L03Lesson learnedThin steel near water needs fatigue counting, not just peak readings.
Made with Modulify