Fig. 01 / Project 05 of 06 / Point cloud
Local grid / 1 : 400
Ribeira Bridge PavilionPorto, 2021
- Area
- 640 m²
- Year
- 2021
- Structure
- Steel
- Status
- Complete
Fig. 02 / Drawing set / Plan, section, elevation, axonometric
Fine lines drawn from the model / point cloud on the last tab
Drawn fromthe same model.
Every drawing below comes from the model the building was built and scanned against, with its grid, levels and the dimensions the site team worked to.
Fig. 03 / Scan vs design / As built against as drawn
Grey under 3 mm / blue over 8 mm
The building,against its drawing.
Drag the handle to compare the design with the latest scan. Each point is coloured by how far the built surface sits from the drawn one.
18 mm / Roof plate tip on the bridge side
Fig. 04 / Construction / Survey to handover
All milestones complete
Construction timeline
- Survey / Done
- Foundations / Done
- Structure / Done
- Envelope / Done
- Handover / Done
- Survey
- Foundations
- Structure
- Envelope
- Handover
Nov 2019 to May 2021 / 18 months
Fig. 05 / Credits / Team
Everyone who built it
Credits
- Client
- Douro River Transit
- Structure
- Ponte Engenharia de Estruturas
- Services
- Douro Sistemas
- Contractor
- Metalúrgica do Freixo
- Scan imagery
- Norrvik
Fig. 06 / Narrative / What the model found
About 200 words
About the project
- Client
- Douro River Transit
- Location
- Porto / Portugal
- Sensors
- 34
The Ribeira Bridge Pavilion is a 640 m² steel pavilion for river transport tickets and shelter at the foot of the Ribeira bridges in Porto. A single folded steel roof, 42 metres long, rests on eleven slender columns set back from the quay, so the view along the Douro stays open beneath it and the old riverfront keeps its line.
Steel this thin on a windy river edge needed proof as well as calculation. Strain gauges and accelerometers were fixed to the roof before it was lifted into place, which made it the first project we monitored from the first day of construction. The highest gust recorded so far reached 31 metres per second, and the roof deflected 18 millimetres at its free edge, within two millimetres of the prediction. Three years of matching data let the client extend the structural inspection interval from six months to a year, and the same gauges now count fatigue cycles at every connection.
Fig. 07 / Energy / 24 months monitored
kWh per m² per month / dashed line is the target
Energy use,month by month.
- Last 12 months
- 41 kWh/m²
- Monthly target
- 3.6 kWh/m²
- Months at or under target
- 14 / 24
- Embodied carbon
- 188 kgCO2e/m²
| Period | Measured |
|---|---|
| Oct 24 | 3 kWh/m² |
| Nov 24 | 3.4 kWh/m² |
| Dec 24 | 4.2 kWh/m² |
| Jan 25 | 4.3 kWh/m² |
| Feb 25 | 4 kWh/m² |
| Mar 25 | 3.4 kWh/m² |
| Apr 25 | 3 kWh/m² |
| May 25 | 2.9 kWh/m² |
| Jun 25 | 3.3 kWh/m² |
| Jul 25 | 3.9 kWh/m² |
| Aug 25 | 3.9 kWh/m² |
| Sep 25 | 3.2 kWh/m² |
| Oct 25 | 2.9 kWh/m² |
| Nov 25 | 3.3 kWh/m² |
| Dec 25 | 4 kWh/m² |
| Jan 26 | 4.2 kWh/m² |
| Feb 26 | 3.9 kWh/m² |
| Mar 26 | 3.3 kWh/m² |
| Apr 26 | 3 kWh/m² |
| May 26 | 2.9 kWh/m² |
| Jun 26 | 3.2 kWh/m² |
| Jul 26 | 3.7 kWh/m² |
| Aug 26 | 3.7 kWh/m² |
| Sep 26 | 2.9 kWh/m² |
Fig. 08 / Materials / Structural mass
Share by weight, as built
| Material | Share |
|---|---|
| Steel | 58% |
| Concrete | 22% |
| Glass | 14% |
| Timber | 3% |
| Other | 3% |
Fig. 09 / Lessons learned / Carried into the next model
03 entries
- L01Lesson learnedFix the gauges before the lift. The first day of load is the one you cannot recreate.
- L02Lesson learnedMeasured deflection within 2 mm of prediction bought a longer inspection interval.
- L03Lesson learnedThin steel near water needs fatigue counting, not just peak readings.