Skip to content

Fig. 01 / Project 03 of 06 / Point cloud

Local grid / 1 : 400

All projects

Ostra Cultural HallGdańsk, 2025

Area
5 200 m²
Year
2025
Structure
Steel
Status
Complete

Fig. 02 / Drawing set / Plan, section, elevation, axonometric

Fine lines drawn from the model / point cloud on the last tab

Drawn fromthe same model.

Every drawing below comes from the model the building was built and scanned against, with its grid, levels and the dimensions the site team worked to.

12345678ABC42 00028 000D1D2D3D4StageRaked seating / 620LobbyN010 mSCALE 1:400

Fig. 03 / Scan vs design / As built against as drawn

Grey under 3 mm / blue over 8 mm

The building,against its drawing.

Drag the handle to compare the design with the latest scan. Each point is coloured by how far the built surface sits from the drawn one.

42 00013 000+0.00+1.10+6.16+13.00+16.00StageRaked seatingSteel truss / 14 panels at 3 000Node T7010 mSCALE 1:300DESIGNAS BUILT

8.4 mm / Truss node T7 above the stage

Fig. 04 / Construction / Survey to handover

All milestones complete

Construction timeline

  1. Survey / Done
  2. Foundations / Done
  3. Structure / Done
  4. Envelope / Done
  5. Handover / Done

Jun 2022 to Mar 2025 / 33 months

Fig. 05 / Credits / Team

Everyone who built it

Credits

Client
Ostra Cultural Trust
Structure
Bałtyk Steel Design
Services
Wydma Engineering
Contractor
Motława Budownictwo
Scan imagery
Norrvik

Fig. 06 / Narrative / What the model found

About 200 words

About the project

Client
Ostra Cultural Trust
Location
Gdańsk / Poland
Sensors
220

Ostra Cultural Hall is a 1 440-seat concert and events hall in the former shipyard district of Gdańsk, built inside the steel frame of a 1950s assembly shed. The original roof trusses were scanned, checked and kept, and the new auditorium sits within them as a separate timber-lined volume, so the industrial structure stays legible above the audience.

Occupancy sensors went in a full season before the interior was finished, while the hall ran temporary events. They showed nine in ten visitors arriving through the two doors nearest the tram stop, with queues of up to eleven minutes at the second door while the far doors stood almost unused. The entrances were redrawn before fit-out: the second door was widened, the cloakroom moved away from it and a new door opened on the tram side. Measured queues fell by 64 percent in the first full season, and the same 220 sensors now run the ventilation on real occupancy instead of a timetable.

Fig. 07 / Energy / 24 months monitored

kWh per m² per month / dashed line is the target

Energy use,month by month.

Last 12 months
72 kWh/m²
Monthly target
6.3 kWh/m²
Months at or under target
12 / 18
Embodied carbon
341 kgCO2e/m²
Monitored energy use for Ostra Cultural Hall, kWh per square metre per month
PeriodMeasured
Oct 24No data
Nov 24No data
Dec 24No data
Jan 25No data
Feb 25No data
Mar 25No data
Apr 256.7 kWh/m²
May 255.5 kWh/m²
Jun 254.7 kWh/m²
Jul 254.3 kWh/m²
Aug 254.4 kWh/m²
Sep 254.9 kWh/m²
Oct 255.9 kWh/m²
Nov 257.3 kWh/m²
Dec 258.5 kWh/m²
Jan 268.7 kWh/m²
Feb 268.3 kWh/m²
Mar 267 kWh/m²
Apr 265.8 kWh/m²
May 264.6 kWh/m²
Jun 263.9 kWh/m²
Jul 263.6 kWh/m²
Aug 263.9 kWh/m²
Sep 264.5 kWh/m²
Monthly energy use per square metre of floor area, Apr 25 to Sep 26. The dashed blue line is the design target.

Fig. 08 / Materials / Structural mass

Share by weight, as built

Share of structural mass by material, Ostra Cultural Hall
MaterialShare
Steel41%
Timber22%
Concrete21%
Glass9%
Other7%

Fig. 09 / Lessons learned / Carried into the next model

03 entries

  1. L01Lesson learnedInstall occupancy sensors a season before fit-out, while the doors can still move.
  2. L02Lesson learnedVisitors follow the tram, not the plan. The busiest door was the one nearest the stop.
  3. L03Lesson learnedVentilation on measured occupancy used 23 percent less energy than the timetable.
Made with Modulify